Contents

                        Executive Summary                                                             

1                      Introduction                                                                          

1.1                   Project Background                                                        

1.2                   Purpose of this Report                                                    

1.3                   Structure of the Report                                                

2                      Air Quality Monitoring                                                     

2.1                   Sampling & Testing Methodology                               

2.2                   Monitoring Methodology and Quality Assurance/ Quality Control (QA/QC)                                                                                                       

2.3                   24 Hour TSP and RSP Air Quality Monitoring          

2.4                   1 Hour TSP Air Quality Monitoring                              

3                      Water Quality Monitoring                                              

3.1                   Monitoring Locations & Frequency                           

3.2                   Sampling & Testing Methodology                               

3.3                   QA/QC Requirements                                                           

3.4                   Baseline Monitoring Results                                        

3.5                   Action & Limit Levels                                                           

4                      Ecology                                                                                    

4.1                   Terrestrial Walkover Survey                                     

4.2                   Baseline Dolphin Monitoring                                        

5                      Conclusions                                                                           

 

Annex A1     Baseline Air Quality Monitoring Results

Annex A2     Copies of Calibration Certificates for Air Quality Monitoring

Annex B       Not Used

Annex C1     Copies of Calibration Certificates for Water Quality & Air Monitoring

Annex C2     Quality Control Report for Laboratory Analysis of Suspended Solids

Annex C3     Baseline Water Quality Monitoring Results

Annex D       Baseline Dolphin Monitoring Report

Annex E       Baseline Monitoring Schedule

Annex F       Weather Conditions during Baseline Monitoring Period


 

List of Tables & Figures

Table 1           Baseline Air Quality Monitoring Period

Table 2           Baseline Water Quality Monitoring Period

Table 3           Baseline Dolphin Monitoring Period

Table 2.1        Monitoring Frequency and Parameters of Air Quality Monitoring Stations

Table 2.2        Air Quality Monitoring Equipment

Table 2.3        Summary of Baseline Air Quality Monitoring Results

Table 2.4        Action and Limit Levels for Air Quality

Table 2.5        Action and Limit Levels for Impact Air Quality Monitoring

Table 2.6        Event & Action Plan for Air Quality

Table 3.1        Locations of Baseline Water Quality Monitoring Stations

Table 3.2        Water Quality Monitoring Parameters and Frequency

Table 3.3        Water Quality Monitoring Equipment

Table 3.4        Methods for Laboratory Analysis for Water Samples

Table 3.5        Action & Limit Levels for Water Quality

Table 3.6        Event & Action Plan for Water Quality

Table 4.1        Date of Baseline Dolphin Monitoring

Table 4.2        Dolphin Encounter Rates (Sightings Per 100 km of Survey Effort) during the Baseline Monitoring Period (September - November 2011)

Table 4.3        Action Level and Limit Level for Dolphin Impact Monitoring

Table 4.4        Derived Value of Action Level (AL) and Limit Level (LL)

Table 4.5        Implementation of Event-Action Plan

Figure 1.1       Layout of HY/2012/08 Contract Components

Figure 2.1       Air Quality Monitoring Stations

Figure 3.1       Water Quality Monitoring Stations

Figure 4.1       Transect for Chinese White Dolphin Monitoring

 

Executive Summary

Under Contract No. HY/2012/08, Dragages ¡V Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section (including the northern landfall) of TM-CLK Link (¡§the Project¡¨).  ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) for the Contract.

According to the requirements of the Environmental Monitoring and Audit Manual (EM&A Manual) which is prepared for the TM-CLKL Project (Register No.: AEIAR- 146/2009), baseline monitoring has been undertaken prior to commencement of the construction works of the Contract.  This Baseline Monitoring Report presents findings of the following baseline monitoring components:

Ÿ   Air Quality;

Ÿ   Water Quality; and

Ÿ   Ecology (baseline dolphin monitoring).

Prior to the commencement of the constructions, HyD employed environmental specialists under Agreement No. CE35/2011 (EP) and Contract No. HY/2011/02 to conduct baseline environmental monitoring of air quality, noise, water quality and ecology to facilitate early commencement of construction of Hong Kong Boundary Crossing Facility (HKBCF) reclamation works and TM-CLKL advance Southern Landfall reclamation works under Contract No. HY/2010/02.  The baseline environmental monitoring was undertaken between September and November 2011 in accordance with requirements in the EM&A Manuals for the Hong Kong Link Road (HKLR), HKBCF and TM-CLKL.  A Baseline Environmental Monitoring Report (Version C) for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects ¡V Investigation (hereafter referred to as ¡§BEMR¡¨) was prepared to fulfill the Environmental Permits¡¦ conditions for HKBCF (including TM-CLKL northern landfall) Project ([1]).

In the present baseline monitoring report, relevant baseline monitoring results for water quality and ecology (baseline dolphin monitoring) presented in the BEMR have been adopted for this Project.  In addition, baseline air quality monitoring has been undertaken in the period of October 2013 to collect baseline air monitoring data for the Project which was not covered by the 2011 baseline monitoring.

The baseline monitoring works undertaken for air quality, water quality and ecology for the Project are presented in Tables 1-2 below.

Air Quality

Table 1           Baseline Air Quality Monitoring Period

Monitoring Stations

Parameters, unit

Baseline Monitoring Period*

ASR1, ASR5, AQMS1, AQMS2 and ASR10

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times per day

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour

17/10/2013 ¡V 31/10/2013

Notes:

*1-TSP and 24-hr TSP were measured at all monitoring stations between 17 and 30 October 2013, except for 24-hr TSP at AQMS1 which was measured between 18 to 31 October 2013. Due to electricity failure at AQMS1 during the measurement of 24-hr TSP on 17 October 2013, 24-hr TSP measurement for AQMS1 was conducted between 18 and 31 October 2013

Details of the baseline air quality monitoring are presented in Section 2.  The collected data were used to establish the Action and Limit Levels for 1-hour Total Suspended Particulates and 24-hour Total Suspended Particulates for the impact monitoring throughout the construction of the Contract. 

Whilst the complete baseline report was submitted after works commencement on 1 November 2013, the majority of construction activities under Contract No. HY/2012/08 are marine works, namely dredging activities for the temporary seawall construction.  Thus no significant dust emission source is anticipated during the initial stage of the construction works under this Contract. 

Table 2           Baseline Water Quality Monitoring Period   

Monitoring Stations

Parameters, unit

Baseline Monitoring Period (1)

IS12, IS13, IS14, IS15, CS4, CS6, SR8, SR9 and SR10A

Ÿ  Temperature(¢XC)

Ÿ  pH(pH unit)

Ÿ  Turbidity (NTU)

Ÿ  Water depth (m)

Ÿ  Salinity (ppt)

Ÿ  Dissolved Oxygen (DO) (mg/L and % of saturation)

Ÿ  Suspended solids (SS) (mg/L)

6/10/2011 ¡V 31/10/2011

Notes:

(1)    3 days per week, at mid-flood and mid-ebb tides, for a period of 4 weeks prior to the commencement of the marine works)

 

Details of the baseline water quality monitoring are presented in Section 3.  The collected data were used to establish the Action and Limit Levels for Dissolved Oxygen (DO), Turbidity and Suspended Solids (SS) for the impact monitoring throughout the construction of the Contract.

 

Ecology

Table 3          Baseline Dolphin Monitoring Period

Date of Baseline Dolphin Monitoring

1

05/09/2011

2

07/09/2011

3

16/09/2011

4

23/09/2011

5

06/10/2011

6

10/10/2011

7

13/10/2011

8

17/10/2011

9

28/10/2011

10

01/11/2011

11

02/11/2011

12

05/11/2011

13

06/11/2011

14

07/11/2011

Baseline dolphin monitoring was undertaken from September to November 2011.  Details on the monitoring methodology, locations and findings are presented in Section 4.  Determination of Action and Limit Levels for dolphin monitoring is also presented under the same section.


 

1                                          Introduction

1.1                                   Project Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010. 

Under Contract No. HY/2012/08, Dragages ¡V Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section (including the northern landfall) of TM-CLK Link (¡§the Project¡¨).  ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) for the Contract.

Layout of the Contract components is presented in Figure 1.1.

1.2                                   Purpose of this Report

The purpose of this Baseline Monitoring Report is to determine the baseline levels of air quality, water quality and ecology (particularly Chinese White Dolphin Monitoring) at the designated monitoring locations around the Project area prior to the commencement of any construction works of the Project.  Such baseline conditions will be used as the basis for assessing environmental impacts, if any, and compliance monitoring during the construction works of the Project. 

Under the requirement of Condition 4.3 of the EP, the Baseline Monitoring Report shall be prepared and submitted to the Director of the Environmental Protection (DEP) at least two weeks before the commencement of any construction works of the Project.   

1.3                                   Structure of the Report

Following this introductory section, the structure of the report is as follows:

Section 2: Air Quality Monitoring
Summarises the air quality monitoring locations and frequency, monitoring methodology and baseline monitoring results, and establish the Action and Limit Levels in accordance with the EM&A Manual.

Section 3:   Water Quality Monitoring
Summarises the water quality monitoring locations and frequency, monitoring methodology and baseline monitoring results, and establish the Action and Limit Levels in accordance with the EM&A Manual.

Section 4: Ecology ¡V Chinese White Dolphin Monitoring
Summarises the Chinese White Dolphin monitoring locations and frequency, monitoring methodology and baseline monitoring results, and establish the Action and Limit Levels in accordance with the EM&A Manual.

Section 5: Conclusion
Concludes the representativeness of the baseline monitoring results for the Project.

2                                          Air Quality Monitoring

The baseline air quality monitoring was conducted between 17 and 31 October 2013.  During the baseline air quality monitoring, 1-hour and 24-hour Total Suspended Particulates (TSP) were measured at all the monitoring locations between 17 and 30 October 2013, except for 24-hr TSP at AQMS1 which was measured between 18 and 31 October 2013 due to electricity failure at AQMS1 during the measurement of 24-hr TSP on 17 October 2013.  Monitoring of 1-hour TSP was carried out at least three times per day while that of 24-hour TSP was conducted daily for fourteen (14) consecutive days.

In addition, as per the requirements under Condition 2.4 of EP-354/2009/A, the Enhanced TSP Monitoring Plan has been prepared under Contract No. HY/2012/08.  Details of the monitoring plan are presented in the Enhanced TSP Monitoring Plan ([2]).

Although the complete baseline report was submitted after works commencement on 1 November 2013, the majority of construction activities under Contract No. HY/2012/08 are marine works, namely dredging activities for the temporary seawall construction.  Thus no significant dust emission source is anticipated during the initial stage of the construction works under this Contract.    

2.1                                   Sampling & Testing Methodology

2.1.1                           Monitoring Parameters & Frequency

The proposed monitoring stations for the baseline air quality monitoring are shown in Figure 2.1.  Monitoring parameters, monitoring period and frequency are detailed in Table 2.1.

Table 2.1        Monitoring Frequency and Parameters of Air Quality Monitoring Stations

Air quality monitoring station

Location

Landuse

No. of Storey

Parameter

Period

Frequency

ASR1

Tuen Mun Fireboat Station

 

Office

1

1-hour TSP


24-hour TSP

0700-1900 for 1-hour TSP


24 hours for 24-hour TSP

 

3 times/ day for 1-hour TSP


Daily for 24-hour TSP

ASR5

Pillar Point Fire Station

 

Office

5

AQMS1

Previous River Trade Golf

 

Bare ground

 

0

AQMS2

Bare ground at Ho Suen Street

 

Bare ground

0

ASR10

Butterfly Beach Park

 

Recreational uses

0

2.1.2                           Monitoring Equipment

High Volume Samplers (HVS) were used to carry out 24-hour TSP monitoring. Direct reading dust meter were also used to measure 1-hour average TSP levels.  The 1-hour sampling was determined periodically by HVS to check the validity and accuracy of the results measured by direct reading method.

Wind data monitoring equipment was set at rooftop of ASR5 (Pillar Point Fire Station) for logging wind speed and wind direction such that the wind sensors are clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months and the wind directions are divided into 16 sectors of 22.5 degrees each.  .

Table 2.1 summarizes the equipment used in the baseline air quality monitoring programme.  Copies of the calibration certificates for the equipment are presented in Annex A2.

Table 2.2        Air Quality Monitoring Equipment

Equipment

Model and Make

HVS Sampler

GMWS-2310 ACCU-VOL

Calibrator

CM-AIR-43 (S/N 9833620)

1-hour TSP Dust Meter

Sibata LD-3B

Wind Anemometer

MetPak, WindSonic

 

2.2                                   Monitoring Methodology and Quality Assurance/ Quality Control (QA/QC)

The air temperature, precipitation and the relative humidity data was obtained from Hong Kong Observatory where the wind speed and wind direction were recorded by the installed Wind Anemometer.  The general weather conditions (i.e. sunny, cloudy or rainy) were recorded by the field staff¡¦s observation on the monitoring days.

2.3                                   24 Hour TSP and RSP Air Quality Monitoring

Instrumentation

High volume Samplers (HVS) completed with appropriate sampling inlets were employed for air quality monitoring.  Each sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complies with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

HVS Installation

The following guidelines were adopted during the installation of HVS:

    Sufficient support was provided to secure the samplers against gusty wind.

    No two samplers were placed less than 2 meters apart.

    The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.

    A minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samples.

    A minimum of 2 meters separation from any supporting structure, measured horizontally was required.

    No furnaces or incineration flues were nearby.

    Airflow around the sampler was unrestricted.

    The samplers were more than 20 meters from the drip line.

    Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

Filter Preparation

Fiberglass filters were used [Note: these filters have a collection efficiency of larger than 99% for particles of 0.3µm diameter].  A HOKLAS accredited laboratory was responsible for the preparation of 24-hr conditioned and pre-weighed filter papers for monitoring team.

All prepared filters were equilibrated in the conditioning environment for 24 hours before weighing.  The conditioning environment temperature was around 25 ¢XC and not variable by more than ¡Ó3 ¢XC; the relative humidity (RH) was <50% and not variable by more than ¡Ó5%.  A convenient working RH was 40%.

Operating/ Analytical Procedures

Operating/analytical procedures for the air quality monitoring were highlighted as follows:

Ÿ   Prior to the commencement of the dust sampling, the flow rate of the HVS was properly set (between 1.1 m3/min. and 1.4 m3/min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50.

Ÿ   The power supply was checked to ensure the sampler worked properly.

Ÿ   On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air quality monitoring station.

Ÿ   The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen.

Ÿ   The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.  Then the filter holding frame was tightened to the filter holder with swing bolts.  The applied pressure should be sufficient to avoid air leakage at the edges.

Ÿ   The shelter lid was closed and secured with the aluminum strip.

Ÿ   The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number).

Ÿ   After sampling, the filter was removed and sent to the laboratory for weighing.  The elapsed time was also recorded.

Ÿ   Before weighing, all filters were equilibrated in a conditioning environment for 24 hours.  The conditioning environment temperature should be between 25¢XC and 30¢XC and not vary by more than ¡Ó3¢XC; the relative humidity (RH) should be < 50% and not vary by more than ¡Ó5%. A convenient working RH is 40%.  Weighing results were used for further analysis of TSP concentrations collected by each filter.

Maintenance and Calibration

The following maintenance/calibration was required for the HVS:

Ÿ   The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working condition.

Ÿ   All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of the baseline monitoring and thereafter at bi-monthly intervals.

2.4                                   1 Hour TSP Air Quality Monitoring

Measuring Procedures

The measuring procedures of the 1-hour dust meter are in accordance with the

Manufacturer¡¦s Instruction Manual as follows:

Ÿ   The 1-hour dust meter is placed at least 1.3 meters above ground.

Ÿ   Set POWER to ¡§ON¡¨ and make sure that the battery level was not flash or in low level.

Ÿ   Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet has been released.

Ÿ   Push the knob at MEASURE position.

Ÿ   Set time/mode setting to [BG] by pushing the time setting switch. Then, start the background measurement by pushing the start/stop switch once. It will take 6 sec. to complete the background measurement.

Ÿ   Push the time setting switch to change the time setting display to [MANUAL] at the bottom left of the liquid crystal display. Finally, push the start/stop switch to stop the measuring after 1 hour sampling.

Ÿ   Information such as sampling date, time, count value and site condition were recorded during the monitoring period.

Maintenance and Calibration

The following maintenance/calibration is required for the 1-hour dust meter;

Ÿ   Check and calibrate the meter by HVS to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.

2.4.1                           Baseline Monitoring Results

The average measured TSP levels for the five (5) air quality monitoring stations are summarized in Table 2.3, and the detailed monitoring data and graphical presentations are presented in Annex A1.  No major dust emission sources was observed in the vicinity of the monitoring stations during the baseline monitoring.  No other activities influencing air quality were identified during the monitoring period, and the weather conditions were generally sunny during the baseline monitoring period.

Table 2.3        Summary of Baseline Air Quality Monitoring Results

Baseline Air Quality Monitoring Station

Average 24-hour TSP Level, µg/m3 (range of data)

Average 1-hour TSP Level, µg/m3 (range of data)

ASR1

128 (66 ¡V 173)

125 (65 ¡V 182)

ASR5

167 (97 ¡V 249)

138 (77 ¡V 211)

AQMS1

127 (85 ¡V 221)

131 (72 ¡V 196)

AQMS2

166 (114 ¡V 221)

135 (76 ¡V 226)

ASR10

129 (65 ¡V 181)

134 (70 ¡V 215)

 

Meteorological Data

Average meteorological data (wind speed, wind direction, pressure temperature, humidity) during the monitoring period was obtained from wind anemometer installed at ASR5 (Pillar Point Fire Station) and results are presented in Annex A1.

2.4.2                           Action & Limit Levels

The Action and Limit Levels were determined in accordance with the Updated EM&A Manual (Table 2.4) and based on the baseline monitoring results, the proposed Action and Limit Levels for Impact Air Quality Monitoring for 24-hour TSP (mg/m3) and 1-hour TSP (mg/m3) are summarized in Table 2.5. 

Table 2.4        Action and Limit Levels for Air Quality

Parameter

Action Level

Limit Level

24-hour TSP Level in mg/m3

For baseline level ≤ 200 mg/m³

Action level = (Baseline*1.3+ Limit level )/2;

 

260

 

For baseline level >200 mg/m³

Action level = Limit level

1-hour TSP Level in mg/m3

For baseline level ≤ 384 mg/m³

Action level = (Baseline*1.3+ Limit level )/2;

 

500

 

For baseline level > 384 mg/m³

Action level = Limit level

 

Table 2.5        Action and Limit Levels for Impact Air Quality Monitoring

Parameter

Air Quality Monitoring Stations

Action Level (mg/m³)

Limit Level (mg/m³)

24-hour TSP (mg/m3)

ASR1

213

260

 

ASR5

238

260

 

AQMS1

213

260

 

AQMS2

238

260

 

ASR10

214

260

1-hour TSP ((mg/m3)

ASR1

331

500

 

ASR5

340

500

 

AQMS1

335

500

 

AQMS2

338

500

 

ASR10

337

500

 

 


Table 2.6        Event & Action Plan for Air Quality

EVENT

ACTION

ET (1)

IEC (1)

SOR(1)

Contractor

Action Level

 

 

 

 

 

1. Exceedance for one sample

 

1. Identify the source.

2. Inform the IEC and the SOR.

3. Repeat measurement to confirm finding.

4. Increase monitoring frequency to daily.

 

1.  Check monitoring data submitted by the ET.

2.  Check Contractor¡¦s working method.

 

1.  Notify Contractor.

 

1. Rectify any unacceptable practice

2.  Amend working methods if appropriate

 

2. Exceedance for two or more consecutive samples

 

1. Identify the source.

2. Inform the IEC and the SOR.

3. Repeat measurements to confirm findings.

4. Increase monitoring frequency

to daily.

5. Discuss with the IEC and the Contractor on remedial actions required.

6. If exceedance continues, arrange meeting with the IEC and the SOR.

7. If exceedance stops, cease

additional monitoring.

 

1.  Check monitoring data submitted by the ET.

2.  Check the Contractor¡¦s working method.

3.  Discuss with the ET and the

Contractor on possible remedial measures.

4.  Advise the SOR on the effectiveness of the proposed remedial measures.

5.  Supervisor implementation of remedial measures.

 

1.  Confirm receipt of notification of failure in writing.

2.  Notify the Contractor.

3.  Ensure remedial measures properly implemented.

 

1.  Submit proposals for remedial actions to IEC within 3 working days of notification

2.  Implement the agreed proposals

3.  Amend proposal if appropriate

 

 

 

EVENT

ACTION

Limit Level

ET (1)

IEC (1)

SOR(1)

Contractor

 

1.  Exceedance

for one sample

 

1.  Identify the source.

2.  Inform the SOR and the DEP.

3.  Repeat measurement to confirm finding.

4.  Increase monitoring frequency to daily.

5.  Assess effectiveness of Contractor¡¦s remedial actions and keep the IEC, the DEP and the SOR informed of the results.

 

1.  Check monitoring data submitted by the ET.

2.  Check Contractor¡¦s working method.

3.  Discuss with the ET and the Contractor on possible remedial measures.

4.  Advise the SOR on the effectiveness of the proposed remedial measures.

5.  Supervisor implementation of remedial measures.

 

1.  Confirm receipt of notification of failure in writing.

2.  Notify the Contractor.

3.  Ensure remedial measures are

properly mplemented.

 

1. Take immediate action to avoid further exceedance

2.  Submit proposals for remedial actions to IEC within 3 working days of notification

3.  Implement the agreed proposals

4.  Amend proposal if appropriate

 

2.  Exceedance for two or more consecutive samples

 

1.  Notify the IEC, the SOR, the DEP

And the Contractor.

2.  Identify the source.

3.  Repeat measurements to confirm findings.

4.  Increase monitoring frequency to daily.

5.  Carry out analysis of the Contractor¡¦s working procedures to determine possible mitigation to be implemented.

6.  Arrange meeting with the IEC and the SOR to discuss the remedial actions to be taken.

7.  Assess effectiveness of he

Contractor¡¦s remedial actions and keep the IEC, the DEP and the SOR informed of the results.

8.  If exceedance stops, cease additional monitoring.

 

1.  Discuss amongst the SOR, ET and the Contractor on the potential remedial actions.

2.  Review the Contractor¡¦s remedial actions whenever necessary to assure their effectiveness and advise the SOR accordingly.

3.  Supervise the implementation of remedial measures.

 

1.  Confirm receipt of notification of failure in writing.

2.  Notify the Contractor.

3.  In consultation with the IEC, agree with the Contractor on the remedial measures to be implemented.

4.  Ensure remedial measures are

properly implemented.

5.  If exceedance continues, consider what activity of the work is responsible and instruct the Contractor to stop that activity of work until the exceedance is abated.

 

1. Take immediate action to avoid further exceedance.

2.  Submit proposals for remedial actions to IEC within 3 working days of notification.

3.  Implement the agreed proposals.

4.  Resubmit proposals if problem still not under control.

5. Stop the relevant activity of works as determined by the SOR until the exceedance is abated.

Note:  ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SOR ¡V Supervising Officer¡¦s Representative


3                                          Water Quality Monitoring

The baseline water quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all monitoring stations for the Project.   Thus, the baseline monitoring results and Action/Limit Level presented in HKZMB Baseline Monitoring Report ([3]) are adopted for this Project.  The detail baseline water quality monitoring methodology and results are presented in the following sections. 

3.1                                   Monitoring Locations & Frequency

The locations of the monitoring stations for the Project are shown in Figure 3.1 and detailed in Table 3.1.

Table 3.1        Locations of Baseline Water Quality Monitoring Stations

Station ID

Type

Coordinates

 

 

Easting

Northing

IS12

Impact Station

813218

823681

IS13

Impact Station

813667

824325

IS14

Impact Station

812592

824172

IS15

Impact Station

813356

825008

CS4

Control / Far Field Station

810025

824004

CS6

Control / Far Field Station

817028

823992

SR8

Sensitive receiver (Gazettal beaches in Tuen Mun)

816306

825715

SR9

Sensitive receiver
(Butterfly Beach)

813601

825858

SR10A

Sensitive receiver
(Ma Wan FCZ)

823741

823495

 

In accordance with the EM&A Manual and the HKZMB Baseline Monitoring Report, baseline water quality monitoring was conducted at Impact stations, Control stations and Sensitive Receivers specified in Table 3.1 three times per week at mid-flood (within + 1.75 hours of the predicted time) and mid-ebb (within + 1.75 hours of the predicted time) tides for four consecutive weeks prior to the commencement of marine works.  The interval between 2 sets of monitoring was not less than 36 hours.

In each monitoring day, two times per monitoring day during mid-ebb and mid flood tides (within + 1.75 hours of the predicted time) at three depths (i.e. 1m below surface, mid-depth and 1m above seabed, except where the water depth less than 6m, mid-depth station may be omitted.  Should the water depth be less than 3m, only the mid-depth station was monitored)

3.2                                   Sampling & Testing Methodology

3.2.1                           Monitoring Parameters & Frequency

Table 3.2 summarizes the monitoring parameters, monitoring period and frequencies of the water quality monitoring.

Table 3.2        Water Quality Monitoring Parameters and Frequency

Monitoring Stations

Parameters, unit

Depth

Frequency

IS12

IS13

IS14

IS15

CS4

CS6

SR8

SR9

SR10A

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

Ÿ SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.

Baseline monitoring: 3 days

per week, at mid-flood and

mid-ebb tides, for a period of

4 weeks prior to the

commencement of the marine

works

 

If the water depth is

less than 3m, mid-depth

sampling only.

 

If water depth less

than 6m, mid-depth

may be omitted.

 

In addition to the parameters presented in Table 3.2, monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby should also be recorded.

3.2.2                           Monitoring Equipment

Dissolved Oxygen (DO) and Temperature Measurement Equipment

The instrument for measuring dissolved oxygen and temperature was portable and weatherproof complete with cable, sensor, comprehensive operation manuals and use DC power source.  It was capable of measuring:

 

¡P            a dissolved oxygen level in the range of 0-20 mg/L and 0-200% saturation; and

 

¡P            a temperature of 0-45 degree Celsius.

 

It has a membrane electrode with automatic temperature compensation complete with a cable.  Sufficient stocks of spare electrodes and cables were available for replacement where necessary.  Salinity compensation was a built-in in the DO equipment.

Turbidity

Turbidity was measured in situ by the nephelometric method.  The instrument was portable and weatherproof using a DC power source complete with cable, sensor and comprehensive operation manuals.  The equipment was capable of measuring turbidity between 0-1000 NTU.  The probe cable was not less than 25m in length.  The meter was calibrated in order to establish the relationship between NTU units and the levels of suspended solids.  The turbidity measurement was carried out on split water sample collected from the same depths of suspended solids samples.

Sampler

A water sampler, consisting of a transparent PVC or glass cylinder of a capacity of not less than two litres which can be effectively sealed with cups at both ends was used.  The water sampler has a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

 

Water Depth Detector

 

A portable, battery-operated echo sounder was used for the determination of water depth at each designated monitoring station.

pH

The instrument was consisting of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device.  It was readable to 0.1pH in a range of 0 to 14.  Standard buffer solutions of at least pH 7 and pH 10 were used for calibration of the instrument before and after use.

Salinity

A portable salinometer capable of recording salinity within the range of 0-40 ppt was used for salinity measurements.

Monitoring Position Equipment

A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message ¡¥screen pop-up¡¦ facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office), or other equipment instrument of similar accuracy,was used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

 

Sample Container and Storage


Following collection, water samples for laboratory analysis were stored in high density polythene bottles (250ml/1L) with no preservatives added, packed in ice (cooled to 4¢XC without being frozen) and kept in dark during both on-site temporary storage and shipment to the testing laboratory.  The samples were delivered to the laboratory as soon as possible and the laboratory determination works were started within 24 hours after collection of the water samples.  Sufficient volume of samples was collected to achieve the detection limit.

Calibration of In Situ Instruments

 

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes were checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter was carried out before measurement at each monitoring event.

 

For the on site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" was observed.

 

Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was also being made available so that monitoring can proceed uninterrupted even when some equipment was under maintenance, calibration, etc.


Table 3.3 summarizes the equipment used in the baseline water quality monitoring program.  All the monitoring equipment complied with the requirements set out in the EM&A Documents.  Copies of the calibration certificates are attached in Annex C1.


 

Table 3.3        Water Quality Monitoring Equipment

Equipment

Model and Make

Qty.

Water Sampler

Kahlsico Water-Bottle Model 135DW 150

4

Multi-parameter Water Quality System

YSI 6820-C-M/YSI 6920

6


Monitoring Position Equipment

¡§Magellan¡¨ Handheld GPS Model eXplorist GC

4

 

 

Instrumentation


A multi-parameter meters (Model YSI 6820-C-M /YSI 6920) were used to measure DO, turbidity, salinity, pH and temperature for all captioned water monitoring stations.

Operating/Analytical Procedures

At each measurement, two consecutive measurements of DO concentration, DO saturation, salinity, turbidity, pH and temperature were taken.  The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement.  Where the difference in the value between the first and second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.

Laboratory Analytical Methods

The testing of all parameters for all stations was conducted by Wellab Ltd. (HOKLAS Registration No.083) with comprehensive quality assurance and control procedures in place in order to ensure quality and consistency in results.  The testing method, reporting limit and detection limit are provided in Table 3.4.

Table 3.4        Methods for Laboratory Analysis for Water Samples

Determinant

Instrumentation

Analytical Method

Reporting Limit

Detection Limit

Suspended Solids (SS)

Weighing

APHA 17e 2540D

0.5 mg/L(1)

0.5 mg/L

Note:

(1)           Limit of Reporting is reported as Detection Limit.

3.3                                   QA/QC Requirements

Calibration of In Situ Instruments

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes were checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter was carried out before measurement at each monitoring event.

For the on-site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" was observed.

Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was also being made available so that monitoring can proceed uninterrupted even when some equipment was under maintenance, calibration, etc.

Decontamination Procedures

Water sampling equipment used during the course of the monitoring programme was decontaminated by manual washing and rinsed clean seawater/distilled water after each sampling event.  All disposal equipment was discarded after sampling.

Sampling Management and Supervision

All sampling bottles were labeled with the sample I.D (including the indication of sampling station and tidal stage e.g. IS1_me_a), laboratory number and sampling date.  Water samples were dispatched to the testing laboratory for analysis as soon as possible after the sampling. All samples were stored in a cool box and kept at less than 4¢XC but without frozen.  All water samples were handled under chain of custody protocols and relinquished to the laboratory representatives at locations specified by the laboratory.  The laboratory determination works were started within 24 hours after collection of water samples.

Quality Control Measures for Sample Testing

Before each round of monitoring, a zero check in distilled water was performed with the turbidity probe of YSI 6820-C-M /YSI 6920 and HANNA HI 8314.  The probe was then calibrated with a solution of known NTU.

QA/QC procedures as attached in Annex C2 are available for the SS analyzed in the HOKLAS-accredited laboratory, WELLAB Ltd.

3.4                                   Baseline Monitoring Results

Baseline water quality monitoring was conducted between 6 and 31 October 2011 for all monitoring stations.  The monitoring results are shown in Annex C3.  Graphical presentation of water quality at the monitoring stations is given in Annex C4.  Detailed weather conditions at the monitoring locations during the baseline monitoring period are shown in Annex F.  The monitoring schedule is shown in Annex E.

During the baseline monitoring period, no marine construction works were observed in the vicinity of all monitoring stations.  The baseline monitoring results are thus considered representative of the ambient water quality.

3.5                                   Action & Limit Levels

The Action and Limit Levels were adopted from the HKZMB Baseline Report.  The Action and Limit Levels for Impact Monitoring of Water Quality for Dissolved Oxygen (DO, mg/L), Turbidity (NTU) and Suspended Solids (SS, mg/L) are summarized in Table 3.5.

Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan, as provided in Table 3.6 should be carried out.

 

Table 3.5        Action & Limit Levels for Water Quality

Parameter

Action Level#

Limit Level#

DO in mg/L (a)

Surface and Middle

Surface and Middle

 

5.0 mg/L

4.2 mg/L

 

 

 

 

Bottom

Bottom

 

4.7 mg/L

3.6 mg/L

 

Turbidity in NTU (Depth-averaged (b), (c))

120% of upstream control station at the same tide of the same day and 95%-ile of baseline data, i.e.,

27.5 NTU

 

130% of upstream control station at the same tide of the same day and 99%-ile of baseline data, i.e.,

47.0 NTU

SS in mg/L (Depth-averaged (b), (c))

120% of upstream control station at the same tide of the same day and 95%-ile of baseline data, i.e.,

23.5 mg/L

130% of upstream control station at the same tide of the same day and 10mg/L for WSD Seawater Intakes at Tuen Mun and 99%-ile of baseline data, i.e.,

34.4 mg/L

 

Notes:

 

 

# Baseline data: data from HKZMB Baseline Water Quality Monitoring between 6 and 31 October 2011.

(a)   For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(b)   ¡§Depth-averaged¡¨ is calculated by taking the arithmetic means of reading of all three depths

(c)    For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

(d)   All figures given in the table are used for reference only, and EPD may amend the figures whenever it is considered as necessary

(e)   The 1%-ile of baseline data for surface and middle DO is 4.2 mg/L, whilst for bottom DO is 3.6 mg/L.

 

 


Table 3.6        Event & Action Plan for Water Quality

Event

ET Leader

         IEC

               SOR

             Contractor

Action level being exceeded by one sampling day

Repeat in situ measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor and SOR;

 

Check monitoring data, all plant, equipment and Contractor's working methods.

 

Check monitoring data submitted by ET and Contractor¡¦s working methods.

Confirm receipt of notification of non-compliance  in writing;

 

Notify Contractor.

Inform the SOR and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Amend working methods if appropriate.

Action level being exceeded by two or more  consecutive sampling days

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with IEC, SOR and Contractor;

 

Ensure mitigation measures are implemented;

 

Increase the monitoring frequency to daily until no exceedance of Action level;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the proposed mitigation measures submitted by Contractor and advise the SOR accordingly;

 

Supervise the implementation of mitigation measures.

Discuss with IEC on the proposed mitigation measures;

 

Ensure mitigation measures are properly implemented;

 

Assess the effectiveness of the implemented mitigation measures.

Inform the Supervising Officer and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Check all plant and equipment and consider changes of working methods;

 

Submit proposal of additional mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR;

 

Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with

IEC, SOR and Contractor;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the proposed mitigation measures submitted by Contractor and advise the SOR accordingly.

Confirm receipt of notification of failure in writing;

 

Discuss with IEC, ET and Contractor on the proposed mitigation measures;

 

Request Contractor to review the working methods.

Inform the SOR and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Check all plant and equipment and consider changes of working methods;

 

Submit proposal of mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR.

 

 

Limit level being exceeded by two or more consecutive sampling days

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with  IEC, SOR and Contractor;

 

Ensure mitigation measures are implemented;

 

Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the Contractor¡¦s mitigation measures whenever necessary to assure their effectiveness and advise the SOR accordingly;

 

Supervise the implementation of mitigation measures.

Discuss with IEC, ET and Contractor on the proposed mitigation measures;

 

Request Contractor to critically review the working methods;

 

Make agreement on the mitigation measures to be implemented;

 

Ensure mitigation measures are properly implemented;

 

Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

Take immediate action to avoid further exceedance;

 

Submit proposal of mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR;

 

Implement the agreed mitigation measures;

 

Resubmit proposals of mitigation measures if problem still not under control;

 

As directed by the Supervising Officer, to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

Note:  ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SOR ¡V Supervising Officer¡¦s Representative

 

 

 


4                                          Ecology

4.1                                   Terrestrial Walkover Survey

Under Contract No. HY/2012/08, only marine works were involved within the work boundary (Figure 1.1), thus terrestrial walkover survey is not considered deemed necessary.  In the case of any land-based works involved under this Contract, a terrestrial walkover survey where works to be undertaken will be conducted.

4.2                                   Baseline Dolphin Monitoring

Baseline dolphin monitoring was undertaken at Northwest Lantau (NWL) and Northeast Lantau (NEL) under the Chinese White Dolphin (CWD) Service Contract No. HY/2011/02 for a period of three months prior to the commencement of the Contract.  The baseline line-transect vessel surveys for dolphin monitoring were conducted in September, October and November 2011 as shown in Table 4.1.  Location of dolphin transect survey is presented in Figure 4.1.  Detailed monitoring results are presented in Annex D. 

Table 4.1        Date of Baseline Dolphin Monitoring

No.

Date

Location

1

05/09/2011

W LANTAU + NW LANTAU

2

07/09/2011

NW LANTAU + NE LANTAU

3

16/09/2011

NW LANTAU + NE LANTAU

4

23/09/2011

W LANTAU + NW LANTAU

5

06/10/2011

NE LANTAU + NW LANTAU

6

10/10/2011

NW LANTAU +NE LANTAU

7

13/10/2011

NE LANTAU

8

17/10/2011

W LANTAU + NW LANTAU

9

28/10/2011

NW LANTAU + W LANTAU

10

01/11/2011

NW LANTAU +NE LANTAU

11

02/11/2011

W LANTAU + NE LANTAU

12

05/11/2011

NW LANTAU + NE LANTAU

13

06/11/2011

NE LANTAU

14

07/11/2011

NW LANTAU + W LANTAU

Notes:

* NW Lantau = Northwest Lantau Survey Area, NE Lantau = Northeast Lantau Survey Area, W Lantau = West Lantau

In total, 112 groups of Chinese White Dolphins, numbering 413 individuals, were observed during the three-month survey.  Most of them were sighted in the West Lantau (WL) and Northwest Lantau (NWL) regions.

Major findings along and near the future alignments of HKLR and TM-CLKL as well as the reclamation site of HKBCF (collectively called ¡§the Site¡¨ below) are summarized as follows:

Ÿ   Dolphins were sighted but not in high concentration near the Site;

Ÿ   Several large dolphin aggregations were seen near the Site;

Ÿ   Several grids had moderate to high dolphin density near the Site;

Ÿ   Several mother-calf pairs were recorded (near alignments of HKLR and TM-CLKL only);

Ÿ   Several feeding activities were sighted along and near the Site; and

Ÿ   Two fishing boat-associated sightings were made near the Site.

Through photo-identification work, 96 individuals were identified from 182 sightings.  Some were sighted over three times during the three-month survey, indicating their frequent use of Hong Kong waters.  Many of them were year-round residents and some were accompanied by calves.  Ranging pattern developed showed that most of the dolphins ranged across the three survey areas including the HZMB work areas.

4.2.1                           Determination of Action and Limit Levels for Dolphin Monitoring

Vessel-based Line-transect Survey Methodology

According to the requirement of the EM&A Manual, dolphin monitoring programme should cover all transect lines in NEL and NWL survey areas twice per month throughout the entire construction period. 

The survey team used standard line-transect methods (Buckland et al. 2001) to conduct the systematic vessel surveys.  For each monitoring vessel survey, a 15-m inboard vessel (Standard 31516) with an open upper deck (about 4.5 m above water surface) will be used to make observations from the flying bridge area.

Two experienced observers (a data recorder and a primary observer) made up the on-effort survey team, and the survey vessel will transit different transect lines at a constant speed of 13-15 km per hour.  The data recorder will search with unaided eyes and fill out the datasheets, while the primary observer will search for Chinese white dolphins continuously through 7 x 50 marine binoculars.  Both observers will search the sea ahead of the vessel, between 270o and 90o (in relation to the bow, which is defined as 0o).  One to two additional experienced observers will be available on the boat to work in shift (i.e. rotate every 30 minutes) in order to minimize fatigue of the survey team members. 

During on-effort survey periods, the survey team will record effort data including time, position (latitude and longitude), weather conditions (Beaufort sea state and visibility), and distance traveled in each series (a continuous period of search effort) with the assistance of a handheld GPS (Garmin eTrex Legend).

Data including time, position and vessel speed will also automatically and continuously be logged by handheld GPS throughout the entire survey for subsequent review.

When dolphins are sighted, the survey team will end the survey effort, and immediately record the initial sighting distance and angle of the dolphin group from the survey vessel, as well as the sighting time and position.  Then the research vessel will be diverted from its course to approach the animals for species identification, group size estimation, assessment of group composition, and behavioural observations.  The perpendicular distance (PSD) of the dolphin group to the transect line will be later calculated from the initial sighting distance and angle.

Survey effort being conducted along the parallel transect lines that are perpendicular to the coastlines will be labeled as ¡§primary¡¨ survey effort, while the survey effort conducted along the connecting lines between parallel lines will be labeled as ¡§secondary¡¨ survey effort.

Data Analysis (Dolphin Encounter Rate)

Encounter rates of Chinese white dolphins (number of on-effort sightings per 100 km of survey effort, and total number of dolphins sighted on-effort per 100 km of survey effort) will be calculated in NEL and NWL survey areas in relation to the amount of survey effort conducted during each month of monitoring survey.  Dolphin encounter rates will be calculated for comparison between the baseline monitoring and impact monitoring results

For the HZMB baseline monitoring results, the encounter rates were calculated using primary survey effort alone (i.e. effort conducted along parallel transect lines that were perpendicular to the coastlines).  Only data collected under Beaufort 3 or below condition would be used for encounter rate analysis.  The average encounter rate of sightings (STG) and average encounter rate of dolphins (ANI) were deduced based on the encounter rates from six events during the baseline period (i.e. six sets of line-transect surveys in North Lantau) using the following formulae: 

 

Total No. of On-effort Sightings

Encounter Rate (STG) = ---------------------------------------------------- x 100

                         Total Amount of Survey Effort (km)

 

Total No. of Dolphins from All On-effort Sightings

Encounter Rate (ANI) = -------------------------------------------------------------------- x 100

                              Total Amount of Survey Effort (km)

These encounter rates will be used for the implementation of Event and Action Plan to examine whether the Action Level or Limit Level should be triggered from the comparison of encounter rates between baseline and impact phase quarterly monitoring periods.

Dolphin Encounter Rates during Baseline Period

During the present three-month study period, the encounter rates of Chinese White Dolphins deduced from the survey effort and on-effort sighting data from the primary transect lines under favourable conditions (Beaufort 3 or below) from each of the survey areas are shown in Table 4.2.

Table 4.2        Dolphin Encounter Rates (Sightings Per 100 km of Survey Effort) during the Baseline Monitoring Period (September - November 2011)

 

Survey Area

Dolphin Monitoring

Encounter rate (STG)
(no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey effort)

 

 

Primary Lines Only

Primary Lines Only

Northeast  Lantau

Set 1

3.34

3.34

Set 2

0.00

0.00

Set 3

3.02

15.11

Set 4

5.92

14.79

Set 5

13.76

73.39

Set 6

9.93

26.49

Average from the six sets

6.00 ¡Ó 5.05

22.19 ¡Ó 26.81

Northwest Lantau

Set 1

1.39

2.77

Set 2

16.57

55.25

Set 3

5.24

24.48

Set 4

8.45

35.47

Set 5

13.13

86.30

Set 6

14.33

83.69

Average from the six sets

9.85 ¡Ó 5.85

44.66 ¡Ó 29.85

Event and Action Plan for Dolphin Impact Monitoring

To define the Action Level (AL) and Limit Level (LL) in comparison with the baseline dolphin encounter rate, the seasonal fluctuation of dolphin encounter rate in NWL and NEL were considered by comparing dolphin encounter rates across the four seasons in order to take the natural fluctuation of dolphin occurrence into account. 

Notably, the natural fluctuation among different seasons can differ by as much as 30%, and in a few extreme cases up to 40-60% upon review of dolphin historical data in North Lantau waters.

Therefore, the approach of 30% and 60% percentage reduction to define the AL and LL, respectively, is reasonable to determine whether the construction activities of TM-CLKL project have caused real significant impact on dolphin occurrence, instead of triggering false alarms prematurely.  Although the exact percentages (30%/60%) for the AL and LL are set somewhat arbitrarily, this is based on careful consideration of the natural fluctuation of dolphin occurrences among different seasons as explained above.

The proposed AL and LL are shown in Tables 4.3 and 4.4:

Table 4.3        Action Level and Limit Level for Dolphin Impact Monitoring

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

STG < 70% of baseline &
ANI < 70% of baseline

STG < 70% of baseline &
ANI < 70% of baseline

Limit Level

[STG < 40% of baseline & ANI < 40% of baseline]

and

STG < 40% of baseline & ANI < 40% of baseline

Notes:

1.            STG means quarterly encounter rate of number of dolphin sightings, which is 6.00 in NEL and 9.85 in NWL during the baseline monitoring period

2.            ANI means quarterly encounter rate of total number of dolphins, which is 22.19 in NEL and 44.66 in NWL during the baseline monitoring period

3.            For North Lantau Social Cluster, AL will be trigger if NEL or NWL fall below the criteria; LL will be triggered if both NEL and NWL fall below the criteria.

Table 4.4        Derived Value of Action Level (AL) and Limit Level (LL)

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

STG < 4.2 & ANI< 15.5

STG < 6.9 & ANI < 31.3

Limit Level

[STG < 2.4 & ANI <8.9]

and

[STG < 3.9 & ANI <17.9]

Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan, as provided in Table 4.5 should be carried out.


Table 4.5        Implementation of Event-Action Plan

Event

ET Leader

IEC

SOR

Contractor

Action Level

1.   Repeat statistical data analysis to confirm findings;

 

2.   Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences;

 

3.   Identify source(s) of impact;

 

4.   Inform the IEC, SOR and Contractor;

 

5.   Check monitoring data.

 

6.   Review to ensure all the dolphin protective measures are fully and properly implemented and advise on additional measures if necessary.

 

1.  Check monitoring data submitted by ET and Contractor;

 

2.  Discuss monitoring results and findings with the ET and the Contractor.

1.   Discuss monitoring with the IEC and any other measures proposed by the ET;

 

2.   If SOR is satisfied with the proposal of any other measures, SOR to signify the agreement in writing on the measures to be implemented.

1.  Inform the SOR and confirm notification of the non-compliance in writing;

 

2.  Discuss with the ET and the IEC and propose measures to the IEC and the SOR;

 

3.  Implement the agreed measures.

Limit Level

1.   Repeat statistical data analysis to confirm findings;

2.   Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences;

3.   Identify source(s) of impact;

4.   Inform the IEC, ER/SOR and Contractor of findings;

5.   Check monitoring data;

6.   Repeat review to ensure all the dolphin protective measures are fully and properly implemented and advise on additional measures if necessary;

7.   If ET proves that the source of impact is caused by any of the construction activity by the works contract, ET to arrange a meeting to discuss with IEC, ER/SOR and Contractor the necessity of additional dolphin monitoring and/or any other potential mitigation measures (e.g., consider to modify the perimeter silt curtain or consider to control/temporarily stop relevant construction activity etc.) and submit to IEC a proposal of additional dolphin monitoring and/or mitigation measures where necessary.

 

1.  Check monitoring data submitted by ET and Contractor;

2.  Discuss monitoring results and findings with the ET and the Contractor;

3.  Attend the meeting to discuss with ET, ER/SOR and Contractor the necessity of additional dolphin monitoring and any other potential mitigation measures;

4.  Review proposals for additional monitoring and any other mitigation measures submitted by ET and Contractor and advise ER/SOR of the results and findings accordingly;

5.  Supervise / Audit the implementation of additional monitoring and/or any other mitigation measures and advise ER/SOR the results and findings accordingly.

1.   Attend the meeting to discuss with ET, IEC and Contractor the necessity of additional dolphin monitoring and any other potential mitigation measures;

2.   If ER/SOR is satisfied with the proposals for additional dolphin monitoring and/or any other mitigation measures submitted by ET and Contractor and verified by IEC, ER/SOR to signify the agreement in writing on such proposals and any other mitigation measures;

3.   Supervise the implementation of additional monitoring and/or any other mitigation measures.

1.  Inform the ER/SOR and confirm notification of the non- compliance in writing;

2.  Attend the meeting to discuss with ET, IEC and ER/SOR the necessity of additional dolphin monitoring and any other potential mitigation measures;

3.  Jointly submit with ET to IEC a proposal of additional dolphin monitoring and/or any other mitigation measures when necessary;

4.   Implement the agreed additional dolphin monitoring and/or any other mitigation measures.


5                                          Conclusions

In accordance with the EM&A Manual of the TM-CLKL Project, baseline monitoring has been undertaken prior to commencement of the construction works of the Contract for the following baseline monitoring components:

Ÿ   Air Quality;

Ÿ   Water Quality; and

Ÿ   Ecology (including baseline dolphin monitoring).

Baseline air quality monitoring was conducted at five (5) monitoring stations (ASR1, ASR5, ASR10, AQMS1 and AQMS2) between 17 and 31 October 2013.  No observable dust nuisance was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient air quality levels.  Action and Limit Levels were established for 1-hour TSP and 24-hour TSP based on the baseline monitoring results.

Baseline water quality monitoring was conducted at seven (9) monitoring stations (IS12, IS13, IS14, IS15, CS4, CS6, SR8, SR9 and SR10A) between 6 and 31 October 2011.  No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels.  Action and Limit Levels were established for DO, SS and turbidity based on the baseline monitoring results.

Baseline Chinese White Dolphin monitoring was conducted in two survey areas (Northeast Lantau and Northwest Lantau) from September to November 2011.  Dolphin sightings, distribution, encounter rate, group size, habitat use, mother-calf pairs and behavior were reported.  Photo-identification and range estimation of identified individuals were also made.  Action and Limit Levels are established based on the dolphin encounter rate with due consideration on seasonal variation in dolphin abundance.


 



([1])     Agreement No. CE 35/2011 (EP) Baseline Envrionmental Monitoring for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects-Investigation.

           http://www.hzmbenpo.com/ep_docs/HKBCF_HY201002/503/Baseline_Report_Version_C.pdf

([2]) ERM (2013) Enhanced TSP Monitoring Plan.  Submitted on 28 October 2013 and subsequently approved by EPD on 1 November 2013.

([3]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.